Worked example
How a project moves through Assurr.
A small home extension, walked stage by stage. Switch between the homeowner and contractor view to see what each side experiences.
Worked example · illustrative only
Single-storey rear extension
Project summary
- Reference
- ASR-0241
- Postcode area
- ME13
- Homeowner
- Sarah M.
- Contractor
- Carter & Sons
- Total value
- £61,850
- Schedule
- 19 October 2026 to 3 March 2027
Milestone 01
Groundworks and foundations
Setting out, excavating strip footings to the engineer’s depth, one skip of spoil, concrete footings, blockwork to damp-proof course, booking building control’s excavation inspection.
£9,000
Evidence record
Footings dug
Photograph · Carter & Sons · 21 October 2026
Building control: excavation inspection
Record · Building control · 22 October 2026
Concrete pour
Photograph · Carter & Sons · 23 October 2026
What this stage covers
Complete when
- Footings are poured to drawing SE-01
- Building control’s excavation inspection is recorded
- Blockwork is level and square at DPC
Milestone 02
Drainage and slab
Rainwater and foul connections to the existing run, hardcore, blinding, damp-proof membrane, 100 mm insulation, 100 mm slab.
£9,850
Evidence record
Building control: drainage test
Record · Building control · 12 November 2026
Cover reset to finished floor level
Photograph · Carter & Sons · 18 November 2026
You raised a query on £750 for the inspection chamber. £9,100 was released while it was answered, and the £750 on 19 Nov.
What this stage covers
Complete when
- The slab is level within 5 mm over 2 m
- The membrane laps the DPC
- The drainage test is recorded by building control
- Every chamber is accessible and set to finished floor level
Milestone 03
Walls to wall-plate
Cavity walls in facing brick to the agreed sample panel, insulated cavity, lintels, the steel opening the rear wall (engineer’s calculation SE-02), wall plate.
£12,000
Evidence record
Building control: steel inspection
Record · Building control · 8 December 2026
Walls at wall-plate, rear elevation
Photograph · Carter & Sons · 10 December 2026
What this stage covers
Complete when
- Walls reach wall-plate height on drawing A-03
- The steel is installed and its inspection recorded
- Cavity trays and weep vents are fitted
Milestone 04
Roof and windows
The lean-to roof structure, membrane, battens and tiles to match, two rooflights, lead flashing, fascia and gutters, one window, the three-panel bifold doors.
£14,000
Evidence record
Delivery note, order 7714
Delivery note · Supplier · 4 January 2027
Glazing certificate
Certificate · Manufacturer · 15 January 2027
Roof tiled, rooflights fitted
Photograph · Carter & Sons · 15 January 2027
Your review. Accept the stage, ask for something to be put right with a reason, or raise a query.
Review the evidence above. Approval requires three confirmations to release the milestone payment.
What this stage covers
Complete when
- The roof is weathertight
- Rooflights, window and bifolds are fitted, operating and undamaged
- The delivery note matches the order
- The glazing certificate is supplied
Milestone 05
First fix and plaster
First-fix electrics to kitchen plan K-02 rev B, including the floor-fed island socket, first-fix plumbing, roof insulation, plasterboard ceilings, skim to walls and ceilings, window and door reveals.
£10,000
Funded and protected for this stage. Work starts once Stage 4 is complete.
What this stage covers
Complete when
- First-fix positions match K-02 rev B
- Plaster is smooth with no cracks or blown areas
- Reveals are square
- First-fix photographs are taken before boarding
Milestone 06
Finishes and handover
Second-fix electrics and plumbing, skirting and architrave, mist coat and two coats, external making good, builder’s clean, building control completion inspection.
£7,000
You’ll be asked to fund this stage before it starts.
What this stage covers
Complete when
- Building control’s completion certificate is supplied
- The electrical installation certificate is supplied
- The snag list is closed
About the figures shown. This is illustrative. In a live project, milestones reference the agreed scope and standards: Building Regulations as the legal floor, applicable British Standards (such as BS 8000), manufacturer specifications, and your contract drawings. Stage 03 in this example would also reference Building Regulations Part A and the structural engineer's calculations. Future payment functionality may be provided through regulated third-party payment infrastructure. Assurr does not currently hold project funds.